DOE G 413.3-7A iii
1-12-2011
TABLE OF CONTENTS
1.0 PURPOSE .................................................................................................................................1
2.0 SCOPE ......................................................................................................................................1
3.0 RISK MANAGEMENT ORGANIZATIONAL BREAKDOWN STRUCTURE, CONCEPT,
AND RESPONSIBILITIES .............................................................................................................2
3.1 Risk Management Organizational Breakdown Structure............................................................................ 2
3.2 Risk Management Organizational Concept ................................................................................................ 3
3.3 Risk Management Organizational Responsibilities .................................................................................... 4
3.3.1 Federal Project Director ......................................................................................................................... 5
3.3.2 Integrated Project Team ......................................................................................................................... 5
3.3.3 Contractor Project Manager ................................................................................................................... 6
3.3.4 DOE/National Nuclear Security Administration Headquarters ............................................................. 6
4.0 RISK MANAGEMENT PROCESS WITHIN THE PROJECT LIFE CYCLE .......................7
4.1 Project Phase Integration ............................................................................................................................ 7
4.2 Risk Planning.............................................................................................................................................. 9
4.3.1 Risk Identification ............................................................................................................................... 10
4.3.2 Assignment of the Risk Owner ............................................................................................................ 14
4.3.3 Assignment of Probability and Consequence ...................................................................................... 14
4.3.4 Assignment of Risk Trigger Metrics .................................................................................................... 15
4.3.5 Risk Register ........................................................................................................................................ 15
4.3.6 Risk Analysis ....................................................................................................................................... 16
4.4.1 Acceptance ........................................................................................................................................... 28
4.4.2 Avoidance/Exploit ............................................................................................................................... 28
4.4.3 Mitigation/Enhance .............................................................................................................................. 29
4.4.4 Transfer/Share ...................................................................................................................................... 30
4.6.1 Risk Monitoring Process Considerations ............................................................................................. 31
4.6.2 Risk Monitoring Methods .................................................................................................................... 32
5.0 RISK DOCUMENTATION AND COMMUNICATION ......................................................35
6.0 TAILORING OF RISK MANAGEMENT ...........................................................................399
7.0 APPLICATION OF CONTINGENCY AND MANAGEMENT RESERVE FOR NON-
M&O CONTRACTS .....................................................................................................................40
8.0 ATTACHMENTS .............................................................................................................
Attachment 1: Risk Breakdown Structure ................................................................................... 1-1
Attachment 2: Risk Status Report ................................................................................................ 2-1
Attachment 3: Risk Responsibility Assignment Matrix .............................................................. 3-1
Attachment 4: Probability Scale/Schedule Consequence Criteria ............................................... 4-1
Attachment 5: Risk Register ........................................................................................................ 5-1
Attachment 6: Cost/Benefit Analysis........................................................................................... 6-1
Attachment 7: Opportunity Matrix .............................................................................................. 7-1
Attachment 8: Risk Identification Checklist ................................................................................ 8-1
Attachment 9: Risk Monitoring Checklist ................................................................................... 9-1
Attachment 10: Management Reserve or Contingency Use Report .......................................... 10-1
Attachment 11: Risk Identification, Development and Use of Contingency and Management
Reserve ....................................................................................................................................... 11-1
Attachment 12: Cost and Schedule Contingency Development Process ................................... 12-1
Attachment 13: Contingency Estimate Inputs and Interface Needs (Supplementary Information)
.................................................................................................................................................... 13-1