The Journal of The Southern African Institute of Mining and Metallurgy VOLUME 107 REFEREED PAPER FEBRUARY 2007
SSuummmmaarryy
One of the most difficult problems in mining
operation is how to determine optimum cut-off
grades of ores at different periods over the
lifespan of the mine that will maximize the net
present value (NPV) of the mine. Maximizing
the NPV of a mining operation, subject to
different constraints is a nonlinear
programming problem. Cut-off grade
optimization is used to arrive at an operating
strategy that maximizes the value of a mine.
Cut-off optimization as a concept has been
known for many years, particularly since
Lane’s latest revolution, but it is still not
widely practised.
Cut-off grade optimization maximizes the
NPV of a project subject to capacity constraints
in the mine, mill and the market. These are
usually expressed as annual limits to the
tonnage mined, tonnage milled and product
sold. At any point in time at least one limit,
and possibly two or all three, will be
constraining the system. For cut-off
optimization to work correctly, capacity
constraints must be independent of the cut-off
grade. The cut-off grade is used to distinguish
ore from waste materials. If the cut-off grade is
too high, much of the mined material will go to
the waste dump area. If the cut-off is too low,
then the input capacity of the entire mining
and mineral processing operations will be fully
stretched, while revenues do not necessarily
increase. The optimal strategy is one that
strikes the correct balance between these two
limits.
This paper describes the determination of a
cut-off grade strategy based on Lane’s (Lane,
1964), algorithm adding an optimization factor
based on the generalized reduced gradient
(GRG) algorithm to maximize the project’s
NPV. In this study, a computer program using
Excel and Visual Basic has been developed to
implement the algorithm. An interactive user-
friendly cut-off grade program was coded
using Visual Basic in a Wwindows based
spreadsheet application (Excel), a well-known
application commonly used by mining profes-
sionals.
The cut-off grade program developed is
used to incorporate the optimization factor (σ)
which is included in the ultimate cut-off grade
equation, which considers the mining (m) cost,
to further maximize the total NPV of the mine
project. σ is the optimization factor and m is
the mining cost per ton. The program solves
gi
cm f F
Psxy
u
i
()
=
++++
()
σ
Determination of optimal cut-off grade
policy to optimize NPV using a new
approach with optimization factor
by A. Bascetin,* and A. Nieto
SSyynnooppssiiss
One very important aspect of mining is deciding what material in a
deposit is worth mining and processing, versus what material
should be considered waste. This decision is summarized by the cut-
off grade policy. The cut-off grade strategy for an open pit mine
influences the annual cash flows and affects the net present value
of a project. The optimization of cut-off grade strategy requires the
knowledge of detailed operational costs, mining sequence, mining
operation, processing, and product constraints, as well as the grade
distribution of a given deposit defined by pit, phase, and different
material types. Cut-off grade optimization algorithms have been
developed in the past. The most common criteria used in cut-off
grade optimization is to maximize the net present value (NPV). This
paper describes the determination of a cut-off grade strategy based
on Lane’s algorithm adding an optimization factor based on the
generalized reduced gradient (GRG) algorithm to maximize the
project’s NPV. The introduced algorithm is a windows based
program developed at Virginia Tech that is based on a series of
Visual Basic routines within a spreadsheet environment (Excel).
The benefits of the methodology are demonstrated using a
hypothetical case study.
Keywords: Cut-off grade optimization, net present value
maximization, generalized reduced gradient algorithm method.
* Istanbul University, Engineering Faculty, Mining
Engineering Department, Istanbul, Turkey.
Virginia Polytechnic Institute and State University,
Mining and Minerals Engineering, Blackburg,
Virginia, USA.
© The Southern African Institute of Mining and
Metallurgy, 2007. SA ISSN 0038–223X/3.00 +
0.00. Paper received Mar. 2006; revised paper
received Jan 2007.
TT
rr
aa
nn
ss
aa
cc
tt
ii
oo
nn
PP
aa
pp
ee
rr
87
Determination of optimal cut-off grade policy to optimize NPV
for the optimization factor (σ), which is a nonlinear problem
(NLP), based on the generalized reduced gradient (GRG)
algorithm by maximizing the project’s NPV.
The algorithm was tested using first the optimization
factor to find the maximum the NPV then it was tested by
removing the optimization factor. The results were examined
and presented in the paper. As a result of the study, the cut-
off grade policy determined by the optimization approach
using the (σ) factor gives a higher NPV than the cut-off
grade policy estimated without the optimization factor. The
results given by the used case study indicate that the impact
of the optimization factor (σ) on the objective function (NPV)
is significant at a $17,889,613.00 increase which is
equivalent to a 5% NPV increment. A NPV sensitivity
analysis, which consisted in varying the optimization factor
(σ) from 0.0 to 12.0 in 1.0 unit increments, indicates—as
calculated by the introduced algorithm—that the maximum
NPV value is at σ = 5.84. This approach provides great
flexibility at the mine planning stage for evaluation of
various economic and grade/ton alternatives.
IInnttrroodduuccttiioonn
Cut-off grade is a geologic/technical measure that embodies
important economic aspects of mineral production within a
mineral deposit. In other words, it is defined not only by the
deposit’s geologic characteristics and the technological limits
of extraction and processing, but also by costs and mineral
prices. Taylor (1972) presents one of the best definitions of
cut-off grade. He defined cut-off grade as any grade that, for
any specific reason, is used to separate two sources of action,
e.g. to mine or to leave, mill or to dump.
Some researchers have developed new optimization
techniques based on Lane’s (Lane, 1964) algorithm to
determine a cut-off grade policy. Cut-off grade optimization
is used to derive an operating strategy that maximizes the
value of a mine. Where the mine’s capacity allows, sacrificing
low-grade material enables the mill to process ore that
delivers a higher cash flow. Hence, the cut-off grade policy
has a significant influence on the overall economics of the
mining operation. The determination of cut-off grade policy,
which maximizes the NPV, is already established in the
industry. It has been realized that, as opposed to constant
breakeven cut-off grade, the optimum/dynamic cut-off
grades, which change due to the declining effect of NPV
during mine life, not only honour the metal price and cash
costs of mining, milling, and refining stages, but also take
into account the limiting capacities of these stages and grade-
tonnage distribution of the deposit (Dagdelen, 1992; Lane,
1988; Dagdelen and Mohammad, 1997). In other words, the
techniques that determine the optimum cut-off grade policy
consider the opportunity cost of not receiving the future cash
flows earlier during the mine life due to limiting capacities
present in the stages of mining, milling, or refining.
The optimization factor indicates the level of optimization
achieved for the cut-off grade strategy calculated by the
algorithm. This paper describes the use of an optimization
factor calculated based on the generalized reduced gradient
(GRG) algorithm to improve optimum cut-off grades.
MMeetthhooddss ooff ccuutt--ooffff ggrraaddee ooppttiimmiizzaattiioonn
As discussed earlier cut-off grade is the criterion normally
used in mining operation to discriminate between ore and
waste within a mineral deposit. Waste may either be left in
place or sent to waste dumps. Ore is sent to the treatment
plant for further processing. Optimizing mine cut-off grades
means to maximize the net present value (NPV) of mining
projects. Cut-off grade directly affects the cash flows of a
mining operation, based on the fact that higher cut-off
grades lead to higher grades per ton of ore; hence, higher
revenues are realized depending upon the grade distribution
of the deposit (Dagdelen, 1993). In any given period, the
allocation of material sent to the mill and the product created
in the refinery for sale are also dependent on the cut-off
grade. It is generally accepted that the cut-off grade policy
that gives higher NPVs is a policy that uses declining cut-off
grades throughout the life of the project. Lane (1964, 1988)
has developed a comprehensive theory of cut-off grade
calculation. Table I shows the notation used in the algorithm.
In his approach K. Lane demonstrates that a cut-off grade
calculation which maximizes NPV has to include the fixed
cost associated with not receiving the future cash flows
quicker due to the cut-off grade decision taken now. The cut-
off grade when the concentrator is the constraint is given
below.
[1]
Where g
m
(i): milling cut-off grade, f: fixed cost, F
i
:
opportunity cost per ton of material milled in Year i, P: profit
($), s: selling price ($/unit of product), y: recovery (%).
The opportunity cost is determined as:
[2]
[3]
Where f
a
is the annual fixed costs,
f
f
c
a
=
F
NPV
C
i
d
i
=
g
cfF
Psy
m
i
=
++
()
88
FEBRUARY 2007
VVOOLLUUMMEE 110077 RREEFFEERREEEEDD PPAAPPEERR
The Journal of The Southern African Institute of Mining and Metallurgy
Table I
The notations of the algorithm
Notatiton Explanation Unit
i Year
N Mine life Years
P Metal price $/oz
s Sales cost $/oz
m Mining cost $/ton
c Processing cost $/ton ore
f
a
Fixed costs $/year
f Fixed cost $/ton
y Recovery %
d Discount rate %
CC Capital costs $
M Mining capacity Tons/year
C Milling capacity Tons/year
R Refining capacity Tons/year
Q
m
Material mined Tons/year
Q
c
Ore processed Tons/year
Q
r
Concentrate refined Tons/year
d is the discount rate, NPV
i
is the NPV of the future cash
flows of the years (i) to the end mine life N, and the C is the
total milling capacity in Year i.
The cut-off grade g
m
(i) depends on the NPV
i
and NPV
i
cannot be determined until the optimum cut-off grades have
been decided. The solution to this type of interdependency
problem is obtained by an iterative approach. In this study, a
computer program using Excel and Visual Basic has been
developed to implement the algorithm. An interactive user-
friendly cut-off grade program, based on K. Lane’s algorithm
was coded using Visual Basic in a Windows based
spreadsheet application (Excel), a well-known application
commonly used by mining professionals (Figure 1).
The cut-off grade program developed is used to
incorporate the optimization factor (σ) which is included in
the ultimate cut-off grade equation, which considers the
mining (m) cost,
[4]
to further maximize the total NPV of the mine project. Where
σ is the optimization factor and m is the mining cost per ton
The program solves for the optimization factor (σ), which
is a nonlinear problem (NLP), based on the generalized
reduced gradient (GRG) algorithm by maximizing the
project’s NPV.
A typical difficulty associated with nonlinear optimization
is that in most cases it is only possible to determine a locally
optimal solution but not the global optimum. Loosely
speaking, the global optimum is the best of all possible
values while a local optimum is only the best in the
neighborhood. One of the most powerful nonlinear
optimization algorithms is the generalized reduced gradient
algorithm method. The GRG algorithm was first developed by
Ladson et al. (1978). This procedure is one of a class of
techniques called reduced-gradient or gradient projection
methods, which are based on nonlinear constraints.
The development of the procedure begins with the
nonlinear optimization problem written with equality
constraints. The idea of generalized reduced gradient is to
convert the constrained problem into an unconstrained one
by using direct substitution. If direct substitution were
possible it would reduce the number of independent variables
to (nm) and eliminate the constraint equations. However,
with nonlinear constraint equations, it is not feasible to solve
the m constraint equations for m of the independent variables
in terms of the remaining (nm) variables and then to
substitute to these equations into the economic model.
Therefore, the procedures of constrained variation and
Lagrange multipliers in the classical theory of maxima and
minima are required. There, the economic model and
constraint equations were expanded in a Taylor series, and
only the first order terms were retained. Then with these
linear equations, the constraint equations could be used to
reduce the number of independent variables. This led to the
Jacobian determinants of the method of constrained variation
and the definition of the Lagrange multiplier being a ratio of
partial derivatives.
gi
cm f F
Psy
u
i
()
=
++++
()
σ
Determination of optimal cut-off grade policy to optimize NPV
TT
rr
aa
nn
ss
aa
cc
tt
ii
oo
nn
PP
aa
pp
ee
rr
89
The Journal of The Southern African Institute of Mining and Metallurgy VOLUME 107 REFEREED PAPER FEBRUARY 2007
Figure 1—The Windows based program for maximization of NPV
The development of the generalized reduced gradient
method follows that of constrained variation. The case of two
independent variables and one constraint equation will be
used to demonstrate the concept, and then the general case
will be described. Consider the following problem.
[5]
Expanding the above in a Taylor series about a feasible
point xk(x
1k
,x
2k
) gives:
[6]
[7]
Substituting Equation [6] into Equation [7] to eliminate
x
2
gives, after some rearrangement:
[8]
In Equation [8] the first two terms are known constants
being evaluated at point xk, and the coefficient of (x
1
x
1k
) is
also a known constant and gives the x
1
the direction to
move. Thus, to compute the stationary point for this
equation, dy/dx
1
= 0; and the result is the same as for
constrained variation which is the term in the brackets of
Equation [8] that is solved together with the constraint
equation for the stationary point. However, the term in the
bracket also can be viewed as giving the direction to move
away from x
k
to obtain improved values of the economic
model and satisfy the constraint equation.
For a better explanation consider;
[9]
[10]
Partition variables into two groups x = (y, z) where y has
dimension m and z has dimension n-m. This partition is
formed such that all variables in y are strictly positive.
Now, the original problem can be expressed as:
[11]
[12]
Key notion is that if z is specified (independent
variables), then y (the dependent variables) can be uniquely
solved. NOTE: y and z are dependent. Because of this
dependency, if we move z along the line z + a Dz, then y will
have to move along a corresponding line y + aDy. Dependent
variables y are also referred to as basic variables.
Independent variables z are also referred to as non-basic
variables.
The basic idea of the reduced gradient method is to
consider, at each stage, the problem only in terms of the
indepented variables. Since y can be obtained from z, the
objective function ƒ can be considered as a function of z
only.
The gradient of ƒ with respect to the independent
variables z is found by evaluating the gradient of ƒ
(B
-1
b-B
-1
Cz, z). The resulting gradient
[13]
is called the reduced gradient.
The generalized reduced gradient solves nonlinear
programming problems in the standard form
[14]
[15]
where h(x) is of dimension m.
The generalized reduced gradient is
[16]
GRG algorithm works similarly to linear constraints.
However, it is also plagued with similar problems as gradient
projection methods regarding maintaining feasibility.
Probably, the most important role of this approach is that
it calculates the optimization factor σ in an iterative approach
updating the remaining reserves, thus the mine life, at every
year, in each iteration, in order to maximize the NPV of the
project. This new approach using a variable optimization
factor basis resulted in an improved total NPV as shown later
in this paper. The program solves for the optimization factor
σ by maximizing the project NPV, which is based on the ore
tonnage–grade distribution and economic parameters of the
mine (see Table IV and Figure 4). The program was
developed at Virginia Tech (Nieto and Bascetin, 2006).
The cut-off grade dictates the quantity mined, processed
and refined in a given period ‘i’, and accordingly, the profits
becomes dependent upon the definition of cut-off grade.
Therefore, the solution of the problem is in the determination
of an optimum cut-off grade in a given period, which
ultimately maximizes the objective function (Asad, 2005). In
addition, using the introduced program, the degree of
precision can be determined, the tolerance, and the degree of
convergence of the results. All of these precision parameters
can be reported in the program as an Excel sheet.
Algorithm procedure of the new cut-off grade
optimization method
The cut-off grade g
m
(i) depends on the NPV
i
, and the NPV
i
cannot be determined until the optimum cut-off grades have
been found. The solution to this type of interdependency
problem is obtained by an iterative approach. This iteration
process belongs to the developed package, which is based on
Excell and can be seen as a flowchart demonstrated in
Figure 2.
The steps of the algorithm as mentioned above
(Equation [1]) are as follows:
(i) read the input files:
a. Economic parameters (price, selling cost,
capacities, etc.)
r f y,z f y,z
hy,z hy,z
T
zy
yz
=
()
−∇
()
()
[]
()
1
subject to h x a ≤ x ≤ b
()
= 0,
minimize
f
x
()
R f y,z f y,z B C
T
zy
=
()
−∇
()
1
s.t. ,
,
By Cz b y 0, z 0
A B.C
+= ≥≥
=
[]
()
with, of course
min
f
y, z
()
s.t. ,
Ax x 0
=
b
min
f
x
()
0
11 2 2
12
=
()
+
()
()
+
()
()
fx
df x x x
d
df x x x
d
k
kk
x
kk
x
yyx
d
d
xxx
d
d
xxx
k
y
x
kk
y
x
kk
=
()
+
()
()
+
()
()
12
11 2 2
Optimize
Subjectto
12
12
:y x,x
:f x,x 0
()
()
=
Determination of optimal cut-off grade policy to optimize NPV
90
FEBRUARY 2007
VVOOLLUUMMEE 110077 RREEFFEERREEEEDD PPAAPPEERR
The Journal of The Southern African Institute of Mining and Metallurgy
b. Grade-tonnage distribution
(ii) determine the COG g
m
(i) by Equation [1];
Setting V = NPV
i
, the initial NPV
i
= 0
(iii) compute the ore tonnage (T
o
) and waste tonnage
(T
w
) from the grade-tonnage curve of the deposit:
a. the ore tonnage (T
o
) and the grade g
c
above
the COG g
m
(i)
b. the waste tonnage (T
w
) that is below the COG
g
m
(i)
c. Also, compute the stripping ratio SR where
SR = (T
w
)/(T
o
)
(iv) Set Q
ci
= C, if T
0
is greater than the milling
capacity, otherwise, Q
ci
= T
0
. Also, set the Q
mi
quantity mined (Q
mi
= Qc(1+SR)) and Q
ri
= Q
c
g
avg
y
(v) determine the annual profit by using the following
equation:
P
i
=(S
i
-r
i
)Q
ri
– Q
ci
( c
i
+ f) – m
i
Q
mi
(vi) adjusting the grade tonnage curve of the deposit by
subtracting ore tons Q
ci
from the grade distribution
intervals above optimum COG g
m
(i) and the waste
tons Q
mi
Q
ci
from the intervals below optimum
COG g
m
(i) in proportionate among such that the
distribution is not changed.
(vii) check, if Q
ci
less than the milling capacity (C), then
set mine life N=i and go to step (viii);
otherwise set the year indicator i = i + 1 and go to
step (ii).
(viii) calculate the accumulated future NPV
i
s based on
the profits P
i
calculated in step (v) for each year
from i to N by the following equation
for
each year i = 1, N where N is total mine life in years.
Total NPV is calculated at this stage considering a
optimization factor equal to zero.
where σ is the optimization factor equal to zero.
(ix) the first iteration is performed by adjusting the
optimization factor s using the GRG method
maximizing the NPV
i
computed in step (viii). If the
computed NPV
i
does not converge, the algorithm
goes to step (ii) and calculates the COG by varying
the embedded optimization factor s. If the
computed NPV converges, the program stops. The
COG gis for years i=1, N is the optimum policy that
maximizes the NPV. Table IV shows COG calculated
for each year using σ.
The algorithm was tested using first the optimization
factor to find the maximum the NPV then it was tested by
removing the optimization factor. The results were examined
and are presented in the next section.
Hypothetical case study and results
Consider the following hypothetical case of an open pit gold
mine (Dagdelen, 1992). The tonnage grade distribution and
gi
cm f F
Psy
u
i
()
=
++++
()
σ
NPV
P
d
i
j
ji
j
N
=
+
()
+
=
1
1
1
Determination of optimal cut-off grade policy to optimize NPV
The Journal of The Southern African Institute of Mining and Metallurgy
VVOOLLUUMMEE 110077 RREEFFEERREEEEDD PPAAPPEERR
FEBRUARY 2007
TT
rr
aa
nn
ss
aa
cc
tt
ii
oo
nn
PP
aa
pp
ee
rr
91
Figure 2—Flowchart of new algorithm for cut-off grade optimization
mine design parameters are shown in Tables II and Figure 3,
respectively. The values in Table II give assumed capacities
and accepted costs to mine this deposit at 2 857 ton/day
milling rate. The mine will be worked at the rate of seven
days a week for 350 days per year.
Table III presents the optimum cut-off grade policy
without the optimization factor. As indicated in Table III, this
optimizing approach gives a total NPV of $354.6 million and
$676.5 million of non-discounted profit.
On the other hand, Table IV presents the results of the
optimum cut-off grade approach using the optimization factor
(σ=5.84). The cut-off grade policy that is determined by this
optimizing approach using the optimization factor (σ) gives a
total NPV of $372.5 million and $638.9 million of non-
discounted profit.
According to the values that are shown in Tables III–IV,
the cut-off grade policy determined by the optimization
approach using the (σ) factor gives a higher NPV than the
cut-off grade policy estimated without the optimization
factor. The results are given graphically in Figure 4. An NPV
sensitivity analysis, which consisted in varying the
optimization factor (σ) from 0.0 to 12.0 in 1.0 unit
increments, indicates—as calculated by the introduced
algorithm—that the maximum NPV value is at σ = 5.84
which can be seen clearly in Figure 5.
Acknowledgement
This work was supported by the Scientific and Technological
Research Council of Turkey and also by the Research Fund of
Istanbul University (Project number: UDP- 724/26042006).
The software can be requested from: [email protected].
Determination of optimal cut-off grade policy to optimize NPV
92
FEBRUARY 2007
VVOOLLUUMMEE 110077 RREEFFEERREEEEDD PPAAPPEERR
The Journal of The Southern African Institute of Mining and Metallurgy
Table III
Optimum cut-off grade policy of the gold mine (without σ)
Year Optimum cut-off grade (oz/ton) Quantity mined Quantity concentrated Quantity refined Profit ($M) NPV ($M)
1 0.096 12.274.288 1.000.000 209158 61.585.935 354.674.647
2 0.092 11.336.481 1.000.000 199710 58.118.871 293.088.712
3 0.088 10.624.419 1.000.000 192537 55.486.385 242.107.246
4 0.084 10.069.606 1.000.000 186947 53.435.245 199.412.274
5 0.081 9.628.546 1.000.000 182504 51.804.650 163.345.006
6 0.078 9.182.735 1.000.000 177583 49.943.365 132.672.494
7 0.076 8.797.020 1.000.000 173216 48.278.930 106.733.475
8 0.073 8.437.322 1.000.000 168992 46.651.502 84.738.244
9 0.072 8.132.220 1.000.000 165372 45.252.454 66.094.563
10 0.070 7.880.241 1.000.000 162369 44.090.812 50.230.905
11 0.068 7.652.378 1.000.000 159528 42.977.995 36.672.630
12 0.067 7.652.378 1.000.000 159528 42.977.995 25.079.582
13 0.066 7.652.378 1.000.000 159528 42.977.995 14.910.242
14 0.065 7.652.378 809551 129146 32.898.270 5.989.768
Total 126.972.390 13.809.551 2.426.118 676.480.404 354.674.647
Table II
Mine design parameters
Parameters Values
Price 500 $/oz
Sales cost 4 $/oz
Processing cost 17 $/ton
Mining cost 1.3 $/ton
Capital costs $154 M
Fixed costs (f
a
) $9.2 M/year
Fixed cost (f) 9.2 $/ton
Mining capacity --
Milling capacity 1.00 Mt/year
Discount rate 14%
Recovery 95%
Figure 3—Grade-tonnage distribution of the deposit
Grade category
Tons (in thousands)
Determination of optimal cut-off grade policy to optimize NPV
The Journal of The Southern African Institute of Mining and Metallurgy
VVOOLLUUMMEE 110077 RREEFFEERREEEEDD PPAAPPEERR
FEBRUARY 2007
TT
rr
aa
nn
ss
aa
cc
tt
ii
oo
nn
PP
aa
pp
ee
rr
93
Table IV
Optimum cut-off grade policy of the gold mine (with σ)
Year Optimum cut-off grade (oz/ton) Quantity mined Quantity concentrated Quantity refined Profit ($M) NPV ($M)
1 0.109 13.568.726 1.000.000 217550 64.065.456 372.564.260
2 0.104 13.317.461 1.000.000 217550 64.392.101 308.498.804
3 0.100 13.094.386 1.000.000 217420 64.617.832 252.014.505
4 0.096 12.261.729 1.000.000 209032 61.539.507 202.293.181
5 0.093 11.613.909 1.000.000 202505 59.144.521 160.755.767
6 0.090 11.099.508 1.000.000 197323 57.242.785 125.737.463
7 0.088 10.684.393 1.000.000 193141 55.708.109 96.007.354
8 0.086 10.345.010 1.000.000 189722 54.453.412 70.627.489
9 0.084 10.064.576 1.000.000 186896 53.416.648 48.865.873
10 0.082 9.830.808 1.000.000 184541 52.552.410 30.140.183
11 0.081 9.634.511 999.998 182563 51.826.583 13.979.900
Total 125.515.017 10.999.998 2.198.243 638.959.363 372.564.260
Figure 4—Comparison of optimization with and without σ, (a) cut-off grade vs. years, (b) profits vs. years
Figure 5—Sensitivity analysis of total NPV vs. different σ values
Years
Cut-off grade ($/oz)
Cut-off grade (with σ) Cut-off grade (without σ)
Years
Optimization factor (σ)
Optimization factor
NPV (M$)
Profits (M$)
Profits (with σ)
Profits (without σ)
Determination of optimal cut-off grade policy to optimize NPV
CCoonncclluussiioonnss
The results given by the case study indicate that the impact
of the optimization factor (σ) on the objective function (NPV)
is significant at a $17,889,613.00 increase, which is
equivalent to a 5% NPV increment. Therefore, the cut-off
grade optimization algorithm presented here is a tool that
improves the cut-off grade policy and serves as a user-
friendly platform for eventual algorithm adaptations such as
the use of cost escalation and simulation for risk analysis.
This approach provides great flexibility at the mine planning
stage for evaluation of various economic and grade/ton
alternatives. The program has been developed within a
Windows environment which is a user-friendly tool, used in
this case, to calculate interactively different mining cut-off
grade scenarios. The other potential benefit of this user-
friendly application is that can be adapted to handle multiple
sources/grades of ore and to incorporate cost escalation
factors based on striping ratios. The research introduced here
uses what we have called the generalized reduced gradient
(GRG) factor, which further maximizes the total project’s
NPV.
RReeffeerreenncceess
ABADIE, J. and CARPENTIER, J. Generalization of the Wolfe Reduced Gradient
Method to the case of nonlinear constraints in optimization, Gletcher,
R. (ed.), Academic Press, New York. 1969.
ASAD, M.W.A. Cut-off grade optimization algorithm for open pit mining
operations with consideration of dynamic metal price and cost escalation
during mine life, Application of Computers and Operations Research in
the Mineral Industry, (APCOM 2005), Tuscon, USA. 2005. pp. 273–277.
D
AGDELEN, K. Cut-off grade optimization, 23rd Application of Computers and
Operations Research in the Mineral Industry, SME, Littleton, Colorado,
USA. 1992. pp. 157–165.
D
AGDELEN, K. An NPV optimization algorithm for open pit mine design, 24th
Application of Computers and Operations Research in the Mineral
Industry, Montreal, Quebec, Canada. 1993. pp. 257–263.
D
AGDELEN, K. and MOHAMMAD, W.A. Multi-mineral cut-off grade optimization
with option to stockpile, SME annual meeting, Denver, Colorado, USA.
1997.
L
ANE, K.F. Choosing the optimum cut-off grade, Colorado School of Mines
Quarterly, vol. 59, 1964. pp. 485–492.
L
ANE K.F. The economic definition of ore, cut-off grade in theory and practice,
Mining Journal, Books Limited, London. 1988.
L
ASDON, L.S., WAREN, A.D., JAIN, A., and RATNER, M. 1978, Design and testing of
a generalized reduced gradient code for nonlinear programming ACM
Trans. Math. Software, vol. 4, 1978. pp. 34–50.
N
IETO, A. and BASCETIN, A. Mining cut-off grade strategy to optimise NPV based
on multiyear GRG iterative factor, Transactions of the Institutions of
Mining and Metallurgy (AusIMM), Section A Mining Technology,
vol. 115, no. 2. 2006. pp.59–63.
T
AYLOR, H.K. General background theory of cut-off grades, Transactions of the
Institutions of Mining and Metallurgy-(AusIMM), Section A—Mining
Technology, 1972. pp.160–179.
94
FEBRUARY 2007
VVOOLLUUMMEE 110077 RREEFFEERREEEEDD PPAAPPEERR
The Journal of The Southern African Institute of Mining and Metallurgy
As part of its research into more cost-effective comminution
technologies, Mintek, specialists in minerals and
metallurgical technology and beneficiation, has commis-
sioned a pilot-scale high pressure grinding roll (HPGR).
The unit, supplied by Polysius, is powered by dual 11
kW motors and can operate at pressures up to 200 bar, with
a nominal throughput of between 0.5 and 2 t/h.
The HPGR is a relatively new technology, which became
commercially available in the mid-1980s. Initially adopted
by the cement industry for replacing a conventional ball mill
for fine grinding, it is now also commonly used in iron ore
processing, for grinding primary ore, as well as in pellet feed
preparation, and for processing diamond ores. Adoption by
the non-ferrous metals sector has been slower, but in recent
years a number of precious- and base-metal producers have
evaluated the HPGR, particularly for ores that are not ideally
suited for semi-autogenous grinding. The technology is now
viewed as having the potential to affect comminution
technology to the same extent as autogenous and semi-
autogenous grinding.
The HPGR uses the principle of interparticle crushing
between two counter-rotating rolls, one of which is fixed
and the other ‘floating’ by means of hydraulic pressure. The
almost pure compressive forces generate a high proportion
of fines, along with extensive micro-cracking in the larger
particles.
As well as being more energy-efficient than conven-
tional technology, the HPGR results in a product with very
favourable characteristics for further downstream
processing,’ explained Jan Lagendijk, Mintek’s Chief
Engineer: Comminution Services. ‘An HPGR in place of
secondary or tertiary crushers can increase the capacity of a
ball mill considerably. Further major benefits are that the
fines produced may result in better liberation, while the
micro-cracking in the coarser product particles may result in
improved mineral and metal recovery in downstream
processes such as flotation and leaching.’
‘The HPGR test work at Mintek will initially focus on
PGM ore processing, and later be extended to other
commodities,’ said Agit Singh, Manager of Mintek’s Mineral
Processing Division. ‘We will be running extensive trials on
different ore types to look at the possibility of reducing the
specific energy consumption in comminution circuits. In
addition, using the HPGR in conjunction with our other
facilities, we will investigate the effect of the process on
downstream unit operations such as dense-media
separation, flotation, and leaching.’
For further information, contact Jan Lagendijk at
Tel.: (011) 709-4550 or e-mail [email protected].
Mintek commissions new grinding roll for
comminution research